3-2.Piping Design - Mitsubishi Electric CITY MULTI PEFY-P22VMS-E-S Data Book

Table of Contents

Advertisement

3. Piping Design
3-2. Piping Design
3-2-1. PUHY-P300-450YRJC-A Piping
OU
A
1st Joint
Fig. 3-2-1A Piping scheme
Piping length
Item
Total piping length
Farthest IU from OU (L1)
Farthest IU from first Joint (L2)
Height between OU and IU (OU above IU) H
Height between OU and IU (OU under IU) H'
Height between IU and IU
OU: Outdoor Unit, IU: Indoor Unit
Piping "A" size selection rule
Outdoor and the first Joint
PUHY-P300YRJC=CMY-Y102SS-G2
PUHY-P350YRJC=CMY-Y102SS-G2
PUHY-P400YRJC=CMY-Y202S-G2
PUHY-P450YRJC=CMY-Y202S-G2
*1.
A>=40m [131ft.], ø12.70mm [1/2in.] ; A<40m [131ft.], ø9.52mm [3/8in.]
Piping"B","C","D","E"size selection rule
Total down-stream Indoor capacity
~ P140
P141 ~ P200
P201 ~ P300
P301 ~ P400
P401 ~ P650
P651 ~ P800
P801 ~
Piping "a","b","c","d","e","f","g" size selection rule
Indoor Unit size
P15,P20,P25,P32,P40,P50,GUF-50RDH ø6.35 [1/4"]
P63,P71,P80,P100,P125,P140
P200
P250
Note1. No Joint after Header; Piping direct to Indoor Unit from Header;
Note2. If the A/C system is designed to use Cooling mode under outside temperature 10°C, H'(OU under IU)
Note3. As bents cause pressure loss on transportation of refrigerant, fewer bents design is better;
Piping length needs to consider the actual length and equivalent length which bents are counted.
Equivalent piping length (m)=Actual piping length+"M" x Quantity of bent.
B
L1
C
L2
D
E
Joint
d
e
IU
IU
Piping in the figure
Max. length
A+B+C+D+E+a+b+c+d+e+f+g
300 [984']
A+C+D+E+g / A+B+c
120 [394']
C+D+E+g / B+c
40 [131']
50 [164']
40 [131']
h1
(mm [in.])
Pipe(Liquid)
Pipe(Gas)
ø9.52 [3/8"] *1
ø22.20 [7/8"]
ø12.70 [1/2"]
ø28.58 [1-1/8"]
ø12.70 [1/2"]
ø28.58 [1-1/8"]
ø15.88 [5/8"]
ø28.58 [1-1/8"]
(mm [in.])
Pipe(Liquid)
Pipe(Gas)
ø9.52 [3/8"]
ø15.88 [5/8"]
ø9.52 [3/8"]
ø19.05 [3/4"]
ø9.52 [3/8"]
ø22.20 [7/8"]
ø12.70 [1/2"]
ø28.58 [1-1/8"]
ø15.88 [5/8"]
ø28.58 [1-1/8"]
ø19.05 [3/4"]
ø34.93 [1-3/8"]
ø19.05 [3/4"]
ø41.28 [1-5/8"]
(mm [in.])
Pipe(Liquid)
Pipe(Gas)
ø12.70 [1/2"]
ø9.52 [3/8"]
ø15.88 [5/8"]
ø9.52 [3/8"]
ø19.05 [3/4"]
ø9.52 [3/8"]
ø22.20 [7/8"]
SYSTEM DESIGN
a
IU
g
f
IU
IU
(m [ft.])
Bent equivalent length "M"
Max. equivalent length
Outdoor unit model
-
PUHY-P300YRJC-A
145 [476']
PUHY-P350YRJC-A
40 [131']
PUHY-P400YRJC-A
-
PUHY-P450YRJC-A
-
15 [49']
-
Joint selection rule
Total down-stream Indoor capacity
~ P200
P201 ~ P400
P401 ~ P650
P651 ~
*PUHY-P450YRJC's first Joint is always CMY-Y202S-G2;
*Concerning detailed usage of Joint parts, refer to its Installation Manual.
Header selection rule
4-branch Header 8-branch Header 10-branch Header
CMY-Y104-G
Total down-stream Indoor capacity <=P200
* CMY-Y108-G can directly connect PUHY-P300-450YRJC;
* CMY-Y1010-G can directly connect PUHY-P300-450YRJC;
* CMY-Y104-G can NOT connect P200,P250 Indoor, but CMY-Y108, Y1010-G can do;
* Concerning detailed usage of Header parts, refer to its Installation Manual.
Note3.
Indoor capacity is described as its model size;
For example, PEFY-P32VMA-E-S, its capacity is P32;
Note4.
Total down-stream Indoor capacity is the summary of the model size of Indoors downstream.
For example, PEFY-P25VMA-E-S+PEFY-P32VMA-E-S: Total Indoor capacity=P25+P32=P57
Note5.
Piping sized determined by the Total down-stream indoor capacity is NOT necessary
to be bigger than the up-stream one.
i.e. A>=B; A>=C>=D
C7-R Rev.
< =
4m
Header
Capped
b
c
IU
IU
IU : Indoor unit , OU : Outdoor unit
M (m/bent [ft./bent])
0.42 [1.38]
0.47 [1.54]
0.50 [1.64]
0.50 [1.64]
Joint
CMY-Y102SS-G2
CMY-Y102LS-G2
CMY-Y202S-G2
CMY-Y302S-G2
CMY-Y108-G
CMY-Y1010-G
<=P400
<=P650
4 - 57

Advertisement