UPS Installation Plan and Unpacking
Table 3-3. 93E MK2 Required Clearances
93E MK2 Required Clearance for paralleled adjacent UPS or UPS and adjacent PDU
Ambient
25
o
C
30
o
C
35
o
C
40
o
C
Notes:
• L1- clearance to the rear wall.
• L2- clearance between the adjacent paralleled UPS or UPS and adjacent PDU. Parallel UPS should be as close
as possible.
• Some models that feature rear connections also require additional rear clearance to enable installation and
connection.
If battery systems are located in the same room as the UPS, the battery manufacturer's
environmental requirements should be followed if they are more stringent than the UPS
requirements. Operating temperatures above the recommended range will result in decreased
battery life and performance, and may reduce or void the battery warranty.
The UPS ventilation requirements are shown in Table 3-4.

Table 3-4. Air Conditioning or Ventilation Requirements During Full Load Operation

93E MK2-10I-9AH-MBS
93E MK2-10I-9AH-MBS
93E MK2-10I-9AH-MBS
93E MK2-10I-9AH-MBS
93E MK2-10I-9AH-MBS
9
L1(mm)
≥600
Model
Power Rating
10 kVA
15 kVA
20 kVA
30 kVA
40 kVA
Eaton 93E MK2 UPS (10-40kVA, 380/400/415V) Installation and Operation
L2(mm)
≤50
CAUTION
Input / Output Voltage
380/380 400/400 415/415
380/380 400/400 415/415
380/380 400/400 415/415
380/380 400/400 415/415
380/380 400/400 415/415
Heat Dissipation (KC/H)
523
862
1149
1723
2298