Installation Checklist
All packing materials and restraints have been removed from each cabinet.
 
The
UPS cabinet is placed in its installed location. Refrain from installing UPS direct under Air con duct.
 
All conduits and cables are properly routed to the UPS and any ancillary cabinets.
 
All power cables are properly sized and terminated.
 
Neutral conductors are installed.
 
A ground conductor is properly installed.
 
Building alarms are wired appropriately. (Optional)
 
LAN drops are installed. (Optional)
 
LAN connections have been completed. (Optional)
 
The REPO device is mounted in its installed location and its wiring is terminated inside the UPS
cabinet. (Optional)
 
A jumper wire is connected between pins 3 and 4 on the REPO terminal block if using a normally-
closed REPO switch. (Optional)
 
All terminal cover plates are installed.
 
Accessories are mounted in installed locations and wiring is terminated inside the UPS cabinet.
(Optional)
 
Air conditioning equipment is installed and operating correctly.
  
The area around the installed UPS system is clean and dust-free. (Eaton recommends that the UPS
be installed on a level floor suitable for computer or electronic equipment.)
 
Adequate workspace exists around the UPS and other cabinets.
 
Adequate lighting is provided around all UPS equipment.
 
A 230 Vac service outlet is located within 7 .5 meters (25 feet) of the UPS equipment.
 
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer,
parallel systems or installations with accessory cabinets.
Parallel System Installation Checklist
Each cabinet in the parallel system is placed in its installed location. Refrain from installing UPS direct
under Air con duct.
 
All conduits and cables are properly routed to the UPSs and to the parallel tie cabinet.
 
All power cables are properly sized and terminated.
 
Neutral conductors are installed between cabinets as required.
 
Ground conductors are properly installed.
 
CAN wiring between the UPSs is properly installed.
 
Pull chain wiring between the UPSs is properly installed.
 
Adequate workspace exists around the UPSs, parallel tie cabinet, and other cabinets.
 
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer, for
parallel systems.
38
Eaton 93E MK2 UPS (10-40kVA, 380/400/415V) Installation and Operation
for

Advertisement

Table of Contents
loading

This manual is also suitable for:

93e

Table of Contents