UPS Installation Plan and Unpacking

3.2.2 UPS System Power Wiring Preparation

The UPS system installation must meet the following guidelines:
• The system must be installed on a level floor suitable for computer or electronic equipment.
• The system must be installed on clean, dust-free, stable concrete, non-corrosive, non-combustible surfaces
only.
Failure to follow guidelines may void your warranty.
The UPS equipment operating environment must meet the weight requirements shown in Table 3-1 and the size
requirements shown in Figure 3-1. Dimensions are in millimeters (inches).
• Refer to national and local electrical codes for acceptable external wiring practices.
• To allow for future kVA upgrades, consider installing a de-rated UPS using wiring and external overcurrent
protection breakers sized for a fully rated UPS.
• For external wiring, use 90°C copper wire. Wire sizes listed in Table 3-5 are for copper wiring only. If wire is run
in an ambient temperature greater than 30°C, higher temperature wire and/or larger size wire may be necessary.
Wire sizes are based on using the specified breakers.
• Material and labour for external wiring requirements are to be supplied by designated personnel.
• If installing an external maintenance bypass, all feeds to the UPS including the Rectifier Input Breaker (RIB) (if
installed) must have a service disconnect independent of the maintenance bypass power path. Most
maintenance bypass solutions provide UPS input feeds derived from but isolated from the maintenance bypass
power path. If the maintenance bypass solution being installed does not provide such functionality, DO NOT use
a single feeder breaker to supply both the UPS and the maintenance bypass.
12
HIGH TOUCH CURRENT EARTH CONNECTION ESSENTIAL BEFORE CONNECTING SUPPLY.
As a result of the connected loads high leakage current is possible. Connection of the earth
(ground) is required for proper product operation. Do not check UPS operation by removal of the
Earth (ground) connection.
The UPS unit is not suitable for IT and corner-earthed power distribution systems.
RISK OF ELECTRIC SHOCK. This ups receives power from more than one source - disconnection
of the AC and the DC source is required to de - energies this unit before servicing. After
disconnecting the utility power and the DC power, authorized service personnel should wait at
least five minutes for capacitor bleed-off before attempting internal access to the UPS module.
Backfeed protection is an internally fitted option on this device. If this option, or an externally fitted
backfeed contactor are not installed. Select backfeed contactor are shown in Table 3-7 and Table
3-8.
The below label should be applied on all primary power isolators installed remote from the
UPS area and on external access points.
Eaton 93E MK2 UPS (10-40kVA, 380/400/415V) Installation and Operation
WARNING
WARNING
CAPACITORS INSIDE
REQUIRE 5 MINUTES TO
DISCHARGE
TO A SAFE LEVEL AFTER
ALL POWER IS REMOVED.
SEE HANDBOOK FOR
INSTRUCTIONS.