4.2.15
Active/Cold Replacement Workflow of the XSCF
BB Control Cable
You can perform active/cold replacement of the XSCF BB control cable in the
following configuration:
Configuration connecting two or more SPARC M12-2S units to a physical partition
Table 4-22

cable.

Table 4-22     Active/Cold Replacement Procedure of the XSCF BB Control Cable
Work
Order
1
2
3
4
5
6
7
8
9
10
96
Fujitsu SPARC M12-2/M12-2S Service Manual ・ January 2023
shows the workflow for active/cold replacement of the XSCF BB control
Task
Checking the operating condition of the
system and the I/O device usage status
Checking the logical domain assignment
status of CPU resources mounted in the
SPARC M12-2S requiring maintenance
Checking the logical domain assignment
status of memory resources mounted in
the SPARC M12-2S requiring maintenance
Releasing I/O resources of the SPARC
M12-2S requiring maintenance from a
logical domain
Releasing the SPARC M12-2S requiring
maintenance from the physical partition
Releasing the SPARC M12-2S requiring
maintenance from the building block
configuration
Placing the SPARC M12-2S requiring
maintenance into the cold state, and
removing the XSCF BB control cable from
the SPARC M12-2S
Installing the XSCF BB control cable on
the SPARC M12-2S, and placing the
SPARC M12-2S that required maintenance
into the hot state
Incorporating the SPARC M12-2S that
required maintenance into the building
block configuration
Confirming that there is no problem with
the replacement XSCF BB control cable
Reference
"9.2 Checking the Operation Status and
Resource Usage Status of Oracle
"3.2.4 Checking the Assignment Status
of Resources" in the Fujitsu SPARC M12
and Fujitsu M10/SPARC M10 Domain
Configuration Guide
"3.2.4 Checking the Assignment Status
of Resources" in the Fujitsu SPARC M12
and Fujitsu M10/SPARC M10 Domain
Configuration Guide
"9.3 Releasing I/O Resources From a
Logical
Domain"
"9.4.3 Dynamically Releasing the
SPARC M12-2S From the Physical
Partition"
"9.6.1 Releasing the SPARC M12-2S
From the Building Block
Configuration"
"22.3 Removing the XSCF BB Control
Cable"
"22.4 Installing the XSCF BB Control
Cable"
"10.4.1 Incorporating the SPARC
M12-2S Into a Building Block
Configuration"
"10.5.3 Checking the FRU Status After
Maintenance"
Solaris"