6.3 | Connecting power cables to storage
enclosure and servers
Connect the 5U84 storage enclosure using the C19-C20 R/A and the two servers using the C13-NEMA
5-15. Connecting to two Power Distribution Units (PDUs) each on separate power phases improves
power availability. For the 5U84 storage enclosure, connect PSU0 to PDU1 and PSU1 to PDU2. For
both servers, connect PWS1 to PDU1, PWS2 to PDU2.