Rigging and lifting should only be done by a professional rigger in accordance with a written rigging
and lifting plan. The most appropriate rigging and lifting method will depend on job specific factors,
such as the rigging equipment available and site needs. Therefore, a professional rigger must determine
the rigging and lifting method to be used, and it is beyond the scope of this manual to specify rigging
and lifting details.

DELIVERY AND STORAGE

To ensure consistent quality and maximum reliability,
all units are tested and inspected before leaving the fac-
tory. Units are shipped completely assembled and con-
taining refrigerant under pressure. Units are shipped
without export crating unless this has been specified
on the Sales Order.
If the unit is to be put into storage, before installation,
the following precautions should be observed:
Ensure that all openings, such as water connections,
are securely capped.
Do not store where exposed to ambient air tempera-
tures exceeding 107°F (42°C).
The unit should be stored in a location where there is
minimal activity to limit the risk of accidental physical
damage.
To prevent inadvertent operation of the pressure relief
devices the unit must not be steam cleaned.
It is recommended that the unit is periodically inspect-
ed during storage.
JOHNSON CONTROLS

INSPECTION

Immediately upon receiving the unit, it should be in-
spected for possible damage which may have occurred
during transit. If damage is evident, it should be noted
in the carrier's freight bill. A written request for in-
spection by the carrier's agent should be made at once.
See "Instruction Manual", Form 50.15-NM for more
information and details.
Major damage must be reported immediately to your
local Johnson Controls representative.

MOVING THE UNIT

Before moving the unit, ensure that the installation site
is suitable for installing the unit and is capable of sup-
porting the weight of the unit and all associated ser-
vices.
The units are designed to be lifted using either lifting
chains or a fork lift.