Chapter 9
Installation Guidelines and Requirements
Your Preinstallation Responsibilities
This chapter reviews preinstallation considerations such as electrical, environmental,
and safety compliances for the C-series platforms. For complete system specifications,
see "System Specifications" on page 35.
This chapter contains the following topics:
Your Preinstallation Responsibilities
Complete the following tasks before installing the system:
Verify that the electrical supply meets all AC and DC power requirements. See
System Specifications
Verify that the site meets all environment specifications. See "Environmental
on page 44 and "System Specifications" on page 35.
Requirements"
Verify that the cables you plan to use meet the specifications, and review the
cabling recommendations. See Cabling Recommendations on page 47.
Verify the operation of all telephone circuits, digital services, and T1 facilities
required for installation.
Ensure that all IP requirements are met, such as IP addresses, subnet masks,
and any specific routing protocol information.
on page 43
on page 46
on page 48
on page 35.
Your Preinstallation Responsibilities
43