Boiler positioning

This section explains how to erect and position the boiler
in the boiler room.
Caution: Risk of system damage due to
frost!
V Set up the heating system in a room safe
from the risk of frost.
Wall clearances
Wherever possible, position the boiler with the
recommended wall clearances. Reducing the clearances
to the minimum makes the boiler more difficult to access.
The boiler base or foundation must be perfectly flat and
level.
At the factory, the burner door hinges are fitted on the
right hand side. The burner door can be reversed so as to
hinge on the left.
Dimen-
sion
A
Recommended
minimum
B
Recommended
minimum
C
Recommended
minimum
L
Chapter 2.10.1, page 10
Tab. 11 Recommended and minimum wall clearances
(dimensions in mm)
Where applicable, allow extra wall
clearances for additional components such
as DHW cylinder, pipe connections, flue
silencer or other flue components, etc.
Logano G225/Logano plus GB225 - We reserve the right to make any changes due to technical modifications.
Wall clearance
1300
1000
700
400
400
100
Fig. 3
Boiler room clearances (boiler positioned on the
left-hand or right-hand side)
Boiler positioning
6 720 615 876-03.1RS