Oven Doors (Simultaneous Doors); Assembly Removal - Vulcan-Hart VC4G Service Manual

Hide thumbs Also See for VC4G:
Table of Contents

Advertisement

VC4G & VC6G SERIES FULL SIZE CONVECTION OVENS - REMOVAL AND REPLACEMENT OF PARTS
12. Reconnect lead wires at the motor, replace
conduit and junction box cover.
NOTE: Check data plate on motor for wiring
schematic. The motor must rotate clockwise when
viewed from the shaft end.
Fig. 35
13. Slide blower onto motor shaft until hub is flush
with end of shaft then tighten set screws.
14. Adjust motor position until blower is parallel to
motor mounting plate as outlined under
BLOWER ADJUSTMENT.
15. Position motor mounting plate on the rear wall
and secure with nuts and washers.
16. Replace the baffle panel and "snorkel".
17. Replace the air baffle on the rear wall at the lower
right hand corner.
18. Remove cardboard from the bottom of the oven
cavity.
19. Install rack guides and racks.
20. Check oven for proper operation.
OVEN DOORS (SIMULTANEOUS

Assembly Removal

1.
Remove the Top Front Cover and Bottom Front
Cover.
2.
Remove the door switch lever.
3.
Remove the top bearing retainers and top
bearings.
4.
Remove the lower door seal strip to expose the
mounting screws of the door assembly.
A.
Remove the two (2) lower sill bolts by the
lower door shaft and the four (4) counter-
sunk screws from the lower sill.
Page 17 of 75
DOORS)
Disconnect the
electrical power to the machine and
follow lockout / tagout procedures.