Installing The Bracket - Biasi Inovia 25S ERP User Manual And Installation Instructions

Wall hung, fanflue, roomsealed, high efficiency gas boiler
Hide thumbs Also See for Inovia 25S ERP:
Table of Contents

Advertisement

250
25
200
All measures are in mm
Fig. 6.1
• When installing the boiler in a cupboard,
cover or alcove allow at least 5 mm per-
manent clearance from the front face of
the boiler. Also ensure sufficient clearance
to allow free access for servicing and the
lowering of the front control panel.
• If the boiler is installed outside, cover the
appliance to protect it against the ele-
ments and add some special anti-freeze
(neutralised) to the c.h. system.
• Before installing the boiler on an existing
c.h. system, flush it out thoroughly before
fitting the boiler, so as to remove muddy
deposits.
It is advisable to equip the system with a
sediment filter, or use a water-treatment
product in the circulating water.
The latter option in particular, not only
cleans out the system, but also has an anti-
corrosive effect by promoting formation of a
protective skin on metal surfaces and neu-
INSTALLATION
tralising gases present in the water.
We recommend the use of a suitable uni-
versal inhibitor to protect the c.h. system
from corrosion.
25
6.3
Precautions
Before mounting the bracket, check that the
dimensions for fitting the exhaust fume duct
are complied with (refer to the leaflet includ-
ed with the flue kit, packed separately).
Utilise the paper template supplied with the
boiler to determine the fixing position for
the bracket and boiler. Securely mount the
bracket to the wall using appropriate fixings
suitable for the type of wall construction and
capable of supporting the total (wet) load.
Refer to the weight given in the technical
data tables specific for each model.

Installing the bracket

- 37 -

Advertisement

Table of Contents
loading

Table of Contents