13-2. Run-In Procedure Using Load Bank Or Resistance Grid

2
3
!
Stop engine.
!
Do not touch hot exhaust pipe, en-
gine parts, or load bank/grid.
!
Keep exhaust and pipe away from
flammables.
NOTICE − Do not perform run-in
procedure at less than 20 volts weld output
and do not exceed duty cycle or equipment
damage may occur.
1
Load Bank
Turn all load bank switches Off. If needed,
connect load bank to 115 volts ac wall
receptacle or generator auxiliary power
receptacle.
2
Welding Generator
Place Welder Selector switch in the A
position (Single Operator) and rotate A/V
control to minimum. Place Process Select-
or switch in Stick position.
3
Weld Cables
1
5
+
Connect load bank or resistor grid to
generator Side A weld output terminals
using proper size weld cables with correct
connectors. Observe correct polarity.
4
Resistance Grid
Use grid sized for generator rated output.
Turn Off grid.
5
Voltmeter
6
Clamp-On Ammeter
Connect voltmeter and ammeter as
shown, if not provided on generator.
Start engine and run for several minutes.
For Load Bank
Set load bank switches and then adjust
generator A/V control so load equals
rated voltage and current of generator
(see nameplate, rating label, or the
specifications section in this manual).
7
2
3
For Resistance Grid
Set grid switches and then adjust gen-
erator A/V control so load equals rated
voltage and current of the generator
(see nameplate, rating label, or the
specifications section in this manual).
Check generator and meters after first five
minutes then every fifteen minutes to be
sure generator is loaded properly.
NOTICE − Check oil level frequently during
run-in; add oil if needed.
It is recommended to run the welding
generator for two hours minimum and up to
four hours under load. Place A/V control in
minimum position, then shut down load
bank or grid to remove load. Run engine
several minutes at no load.
!
Stop engine and let cool.
7
Engine Exhaust Pipe
Repeat procedure if wetstacking is pres-
ent.
4
6
S-0683 / S-0684
OM-262 752 Page 73