This section is intended to assist the operator with the initial
start-up of the portable generator. It is extremely important
that this section be read carefully before attempting to use
the generator in the field.
Before starting the Engine
1. Be sure to disconnect all electrical loads from the
generator prior to starting the engine.
2. NEvER start the engine with the main circuit breaker
in the ON position. Always place circuit breaker
(Figure 10) in the OFF position before starting.
Figure 10. Main Circuit Breaker (OFF)
starting the Engine (Recoil start)
1. Place the engine fuel valve lever (Figure 11) in the ON
position.
Figure 11. Engine Fuel Valve Lever (ON)
2. Place the choke lever (Figure 12) in the ClOsEd
position if starting a cold engine.
CLOSED
Figure 12. Choke Lever
ga2.5HR 60 hz gENERATOR • OpERATiON ANd pARTs mANuAl — REv. #0 (12/15/14) — pAgE 23
CHOKE
LEVER
OPEN
3. Place the choke lever (Figure 12) in the OpeN position
if starting a warm engine or the temperature is warm.
4. Place the engine ON/OFF switch (Figure 13) in the
"ON" position.
Figure 13. Engine ON/OFF Switch (ON)
5. Grasp the starter grip (Figure 14) and slowly pull it
out. The resistance becomes the hardest at a certain
position, corresponding to the compression point. Pull
the starter grip briskly and smoothly for starting.
Figure 14. Starter Grip
NOTICE
dO NOT pull the starter rope all the way to the end.
dO NOT release the starter rope after pulling. Allow it
to rewind as soon as possible..
6. If the engine has started, slowly return the choke lever
(Figure 12) to the OpeN position. If the engine has not
started repeat steps 1 through 5.
7. Before the generator is placed into operation, run the
engine for 3-5 minutes. Check for abnormal smells,
fuel leaks, and noises that would associate with loose
components.