Unpacking/Setting Up - Continental Girbau CG75-85 Installation Manual

Gas dsi/electric/steam
Hide thumbs Also See for CG75-85:
Table of Contents

Advertisement

10. The dryer must be installed with provisions for adequate combustion and make-up air supply.
CAUTION: This dryer produces combustible lint and must be exhausted to the outdoors. Every 6
months, inspect the exhaust ducting and remove any lint build up.
IMPORTANT: Dryer must be installed in a location/environment, which the ambient
temperature remains between 40º F (4.44º C) and 130º F (54.44º C).
B. UNPACKING/SETTING UP
Remove protective shipping material (i.e., plastic wrap and/or optional shipping box) from dryer.
IMPORTANT: Dryer must be transported and handled in an upright position at ALL times.
The dryer can be moved to its final location while still attached to the skid or with the skid removed. To unskid
the dryer, locate and remove the four (4) bolts securing the base of the dryer to the wooden skid. Two (2) are
at the rear base (remove the back panel for access), and two (2) are located in the bottom of the lint chamber.
To remove the two (2) bolts located in the lint chamber area, remove the lint door.
1. Leveling Dryer
The dryer is equipped with four (4) leveling legs, one (1) at each corner of the base. Two (2) are located
at the rear of the dryer base, and two (2) are located in the lint chamber (coop). To increase bearing life
and improve efficiency, the dryer should be tilted slightly to the rear.
11

Advertisement

Table of Contents
loading

Table of Contents