1. Installation

Boilers should be installed according to binding rules and norms. The requirements of norm
PN 87/B 02411 according building of solid fuel boiler room, norm PN 91/B 02413 according
open system boilers' production and norm PN-B-02414:1999 according to safety appliances in
pressurized systems should be taken into account.
These norms and rules should be followed, however, caution is required as national rules in
countries to which the product is sold may replace above mentioned norms.
In case of boiler assembly outside Poland, rules and norms should be followed according to solid
fuel boiler assembly in countries in which the boiler is sold.
Gasification boilers ORLIGNO 200 are adjusted for installations in pressurized systems.
1. Boiler room height should be at least >2,2 m for easier boiler cleaning.
2. Distance from boiler room walls should allow for free access to boiler sides and should be at
least as shown on picture „ORLIGNO 200 placement".
3. Boiler room should be free of any electric installation not intended for boiler installation.
Pic.1 ORLIGNO 200 placement.