4.4 Scope of delivery

The weighing system is supplied with the following components:
-
Load carriers
-
FIS weighing terminal
-
Operating instructions

4.5 Levelling the weighing system

The weighing system is levelled in the factory using the foot screws. Please
check that all 4 foot screws rest evenly on the supporting area.
The bubble level may also be installed underneath the load plate on small load
carriers.
Please compensate for any unevenness by adjusting the foot screws.

4.6 Mains connection

A separate mains switch is not available.
Maximum weighing accuracy is reached following a short warm-up period. It is
favourable to leave the weighing terminal connected to the mains voltage for
the entire working day.
A consistent operating temperature and highest possible balance accuracy are
achieved in this way.

4.7 Power supply

4.7.1 Installation of the power supply by the customer

Installation of the power supply for the connection of our equipment must be
carried out in compliance with the international standards and the regulations
deriving from these. They mainly include the recommendations of at least
one of the following commissions:
-
International Electrotechnical Commission
-
European Committee for Electrotechnical Standardisation
-
Association of German Electrical Engineers
Our equipment is designed according to VDE protection class III (protective low
voltage ).