Appendix A. Forms

A.1 Checklist for Completed Installation of Cold Row CW
1. Proper clearances for service access have been maintained around equipment.
2. Equipment is level and mounting fasteners are tight.
3. Field-installed piping completed.
4. All field installed piping leaks tested.
5. Condensate drain line connected.
6. Water supply line connected to humidifier (if applicable). If manual cut-off valve is installed, open valve.
7. Humidifier "On/Off/Drain" switch is in "On" position.
8. Filters installed.
9. Incoming line voltage matches equipment nominal nameplated rating ± tolerances.
10. Main power wiring connections to the equipment, including ground, have been properly installed.
11. Customer-supplied main power circuit breaker (HACR type) or fuses have proper ratings for equipment installed.
12. All wiring connections are tight.
13. Foreign materials have been removed from inside and around all equipment installed (shipping materials, construction
materials, tools, etc.).
14. Inspect all piping connections for leaks during initial operation.