Commissioning
6 Commissioning
Check the following requirements before commissioning:
• Correct connection of the AC (grid) cable
• Full connection of the DC cables (PV strings)
• Unused DC plug connectors on the underside of the housing are sealed with protective caps
• The housing cover is securely screwed in place
• The Electronic Solar Switch is securely plugged
• The line circuit breaker is laid out correctly
Commissioning Procedure
1. Switch on the line circuit breaker.
2. During the day, an illuminated or blinking green
LED signals fault-free operation. If this is the case,
commissioning was completed successfully.
There is no display available for displaying due to
a lack of radiation at night.
3. The meaning of the yellow and red LEDs as well as
the error and status messages on the display are
described in the user manual provided.