step 5: commissioning

Pressure test point

Use the oven burner. From inside the oven
remove the burner cowl. Remove the small
screw at the LHS of the burner cradle.
Slide the burner to the left to access the
injector.
Connect suitable T-piece (incorporating
a 115 injector) to the injector. Connect
manometer to the T-piece, and turn oven
control to full on to check pressure.
Replace in reverse order.

Burner aeration

All burners have fixed aeration and no
adjustment is possible.
Pressure setting
Cat I2H Natural Gas G20 @ - 20mbar
Electrical systems check
In the event of an electrical fault the
preliminary electrical system check (earth
continuity, short circuit, polarity and
resistance to earth) must be carried out.
installation instructions

oven ignition

Push in and turn the main oven control
knob anti clockwise to the 'FULL ON'
position (gas mark 9). The ignition
system will spark automatically. Push in
the control knob to ignite the gas. The
sparking will stop. If after 15 seconds, the
burner has not lit, turn off the oven and
leave the compartment door open. Wait at
least one minute before a further attempt
to ignite the burner.
Do not hold the control knob in for more
than 15 seconds.
Turn the control knob clockwise to the
required setting.
To turn off, return the control knob to the
"off" position.
Grill
1. The door must be open for grilling.
2. Push in and turn the control knob
Before leaving the installation
Show the customer how to ignite the oven
and operate the grill and give them this
handbook. Thank you.