08 27224 00 - Prima 60G
Step 5: Commissioning
Pressure test point
Use the oven burner. From inside the
oven remove the burner cowl. Remove
the small screw at the LHS of the
burner cradle. Slide the burner to the
left to access the injector.
Connect
suitable
(incorporating a 1.25mm injector) to
the injector. Connect manometer to
the T-piece, and turn oven control to
full on to check pressure.
Replace in reverse order.
Burner aeration
All burners have fixed aeration and no
adjustment is possible.
Pressure setting
Cat I
G20 Natural Gas @ - 20mbar
2H
Electrical systems check
In the event of an electrical fault the
preliminary electrical system check
(earth continuity, short circuit, polarity
and resistance to earth) must be
carried out.
26/1/05
9:22 am
Page 26
Installation Instructions
Oven
1. Push in and turn the control knob
2. Adjust to the required setting.
3. The burner may not come on to a
T-piece
Grill
1. The door must be open for the grill
2. Push in and turn the control knob
3. Close the door, and check that the
Before leaving the installation
Show the customer how to ignite
the oven and grill and give them this
handbook. Thank you.
24
anticlockwise to gas mark 9.
full rate unless the oven door is
closed.
The oven burner operates at a low
rate for up to 60 seconds until the
flame supervision device opens
and full gas rate is obtained.
burner to ignite.
clockwise to the grill symbol.
burner goes out.
The grill burner will re-ignite when
the door is opened again.