Chapter 2 Installation

2.4 Mechanical Installation

The UPS is suitable for resistive-capacitive load (like computer), resistive load and micro-inductive load. It is not suitable for purely
inductive load or purely capacitive load (like motor, air-conditioner and duplicator), nor can it be connected to half-wave rectifier
load.
Two installation modes are available: tower installation and rack installation. You can select an appropriate installation
mode according to the actual conditions.
According to the different configuration requirements, the UPS has two configurations: battery modules excluded, and
four battery modules. For tower installation, you should prepare the battery rack and battery cabinet for installing the
battery modules; for rack installation, the battery modules and the UPS can be installed in the same rack together.

2.4.1 Tower Installation

1. Assemble a pair of support bases (accessories) and a support base extension (accessory) together through
fastenings, as shown in Figure 2-1.
2. Repeat step 1 to connect another pair of support bases with a support base extension.
3. Place the UPS on the support bases and support base extensions, as shown in Figure 2-2.
For tower installation, two pairs of support bases should be placed respectively at both sides of the UPS, as shown in Figure 2-2.
Otherwise, the UPS may be dumped.
Support base
Support base extension
Figure 2-1 Connecting the support base with support base extension
Support base
Figure 2-2 Installation complete
Liebert ITA 16kVA/20kVA User Manual
Note
Fastening
Support base
UPS
Note