Installation

Vent Installation

In addition to the requirements below, follow the requirements provided with the vent.
Vertical Termination
Use a roof flashing and storm collar
whenever passing through the roof
Use a firestop whenever
passing through a ceiling
8-5/8"
or
10"
8-5/8"
or
10"
Maintain a minimum 1" clearance (2" in
some cases - see "Clearances") from
vent to any combustible
Apply high-temperature silicone to the inner and outer pipe before assembling the sections (on the
male, upper section). This seals the inner pipe from the outer pipe. Slide the sections together and
turn 1/4 turn until the sections lock in place. Install three metal screws through each joint to lock the
outer section in place (see the instructions included with the vent for further details).
Horizontal sections require a 1/4" rise every 12" of travel
Horizontal sections require non-combustible support every three feet (e.g.: plumbing tape)
Travis Industries
Minimum framing
for fire stop
Use a support box
on exposed vent
Use a firestop whenever
passing through a wall
Minimum
Framing for
wall thimble
9 3 5 0 8 1 1 8
(for qualified installers only)
Apply a 1/8" (3 mm)
bead of high-
temperature silicone
to the inner and
outer pipe. The
silicone must seal
the inner pipe from
the outer pipe.
Vertical Vent
Requirements
Maintain a minimum 1"
clearance from vent to
any combustible
Horizontal Vent
Requirements
Horizontal Termination
2 7 0 9 0 0
1 7