UPS System Installation
4.9

Installing Interface Connections

4.9.1

Installing Building Alarm Connections

To install wiring:
1.
Verify the UPS system is turned off and all power sources are removed. See Chapter 6, "UPS Operating
Instructions, " for shutdown instructions.
2.
To locate the appropriate terminals and review the wiring and termination requirements, see
paragraph 3.2.3, Table 4-1, Figure 4-10, Figure 4-11, and Figure 4-12.
Mini-Slot Communication Bays
(See Figure 4-11 for detail)

Figure 4-10. Interface Terminal Locations

4-12
Eaton 9E UPS (20–30 kVA, 208/220V) Installation and Operation Manual 164202124—Rev 2
Interface Terminals
(See Figure 4-11 for detail)
Back
Top Rear Panel
www.eaton.com/powerquality