Assembling D-SUB connector (CN-A302)
1. Remove vinyl sheath of cores by 3 mm.
2. Pass the cores through shrink tubing (local supply).
3. Solder cores to connector pins referring to the interconnection diagram at the back of this
manual.
4. Assemble the connector.
2.3.2 Connecting cable between processor unit and monitor unit
For the FURUNO-supplied monitor, connect the cable (10S2074 or 1022075) from the
processor unit (FSV-8402) to the CN-A302 – CN-A308 connectors on the monitor unit
(FSV-2400).
Attach connector from processor unit and control unit as below.
1. Unfasten four screws (M4×10) at the rear of the monitor to loosen the cable cover.
2. Lift and pull the cable cover to remove it.
3. Unfasten two screws (M4×10) to remove the clamp cover.
4. Lay the monitor and control cables on the clamp, and then reattach the clamp plate to fix
cables.
5. Connect eight connectors referring to the instruction sticker by the connector board.
6. Reattach the cable cover.
2-6
Assembling D-sub connector
Fold back shield onto cable,
and wrap with shield tape.