Section 11 - W7220 JADE™ Economizer Module
When all settings match and are shown in green letters, you can click "Start Checkout" button.
As you go through the check out process you will need to observe the movement of the dampers
and confirm the contacts are made to turn on the stages of compressor on the roof top unit.
When each step is confirmed as working, click the Passed button to move to the next test. If you
have a failure, example damper failed to open, click the Failed button below to move to the next
step.
Do not interrupt a function while it is in process. Wait until the function check is complete then
you can stop the test process.