Figure 2.15 200 To 240 V Redundant Power Supply Configuration (Primary Power Feed, Redundant Power Supply) - Fujitsu PRIMEQUEST 1000 Series Hardware Installation Manual

Hide thumbs Also See for PRIMEQUEST 1000 Series:
Table of Contents

Advertisement

PRIMEQUEST 1000 Series Hardware Installation Manual
CHAPTER 2 Connection Information
FIGURE 2.15 200 to 240 V redundant power supply configuration (primary power feed, redundant power
supply)
*1 Power cables (AC#0 to AC#1) are connected to PSUs (PSU#0 to PSU#1) on a one-to-one basis.
*2 This change to the power supply configuration requires a redundant power supply (200 V) for the PCI_Box, and
the power supply must be prepared separately.
*3 The power distribution box must be prepared separately.
*4 To use a power distribution box, it must meet the breaker characteristics for the customer's distribution panel.
(See
2.6 Shutoff Characteristic of the Customer's Distribution Panel (Only When Connected to the Power
Distribution
Box).)
200 to 240 V dual power feed configuration
35