If you have other devices to install or remove, do so now. Otherwise, go to
"Completing the installation."
Completing the installation
To complete the installation, complete the following steps:
1. If you removed any air baffles, reinstall them (see "Replacing the DIMM air
2. If you removed the server cover, replace it (see "Replacing the cover" on page
3. Install the server in the rack cabinet (see the Rack Installation Instructions that
4. Reconnect the cables and power cords (see "Connecting the cables" on page
5. Update the server configuration (see "Updating the server configuration" on
6. Slide the server back into the rack, if necessary.
Replacing the DIMM air baffle
To install the DIMM air baffle, complete the following steps:
1. Read the safety information that begins on page vii and "Installation guidelines"
2. Turn off the server and peripheral devices and disconnect the power cords and
3. Align the DIMM air baffle over the DIMMs so that the baffle pin on the left side
recessed rings either parallel or perpendicular to the front bezel.
Battery
retention clip
Posts
Microprocessor 2
air baffle
Rings
c. Take the battery retention clip and place it underneath the other tab while
pressing release tab toward the front of the server; then, press it down until
it snaps in place to hold the battery carrier firmly in place.
baffle" and "Replacing the microprocessor 2 air baffle" on page 86).
87).
come with the server for instructions).
87).
page 88).
on page 46.
all external cables (see "Turning off the server" on page 33).
of the air baffle aligns with the pin hole next to DIMM connector 8 on the system
Battery
Posts
Battery
mounting
slots