Summary of Contents for Dyness RV12200

  • Page 1 RV12200 USER MANUAL Battery Module 12.8V/200Ah File version-20231114-V2-EN Information might be subject to change without notice during product improving.
  • Page 2: Table Of Contents

    Equipment installation ..........................14 4 Use, maintenance and troubleshooting ................19 Instructions for use and operation of the battery system ............19 Alarm description and processing ....................20 Analysis and treatment of common faults ..................21 ©Dyness reserves the copyright of this document.
  • Page 3: Statement Of Law

    Copyright of this document belongs to Dyness Digital Energy Technology Co., LTD.No part of this documentation maybe excerpted, reproduced, translated, annotated or duplicated in any form or by any means without the prior written permission of Dyness Digital Energy Technology Co., LTD. Infringement will be prosecuted.
  • Page 4: Safety Precautions

    Please charge the battery in 18 hours after it discharges fully and starts over-discharging protection. Formula of theoretical standby time: T=C/I (T is standby time, C is battery capacity, I is total current of all loads). ©Dyness reserves the copyright of this document.
  • Page 5: Preface

    Preface Manual description The RV12200 lithium iron phosphate battery energy storage system can provide energy storage solutions for photovoltaic power generation users through parallel combination. During the day, the excess power of photovoltaic power generation can be stored in the battery.
  • Page 6: Introduction

    Brief Introduction RV12200 lithium iron phosphate battery system is a standard battery system unit, customers can choose a certain number of RV12200 according to their needs, by connecting parallel to form a larger capacity battery pack, to meet the user's long-term power supply needs.(It is forbidden to use in series)
  • Page 7 After the battery life is terminated, the battery can continue to be used after it recycled by the professional recycling organization and do not discard it at will Dangerous goods warning label on the side of the battery module ©Dyness reserves the copyright of this document.
  • Page 8: Product Specification

    DC12.8V 200Ah 26kg Performance Parameter Table 2-2 RV12200 performance parameter Nominal Voltage 12.8V Work Voltage Range 11.4~14.4V Nominal Capacity 200Ah Nominal Energy 2.56kWh Nominal Power 1.28KW Max Power 2.56KW Rated Charging Current 100A ©Dyness reserves the copyright of this document.
  • Page 9: Interface Definition

    Interface Definition RV121200product panel interface configuration and function. This section details the interface functions of the front panel of the device. 3 4 5 6 Figure 2-1 RV12200 The sketch of interface Table 2-3 Interface Definition Name Definition Positive socket...
  • Page 10 PIN11 Green/White PIN12 Blue CANH PIN13 Blue/White CANL PIN14 Green Reserve PIN15 Brown/White Reserve PIN16 Brown Reserve Table 2-5 SOC/ALM/RUN Light instructions Battery State LED1 LED2 LED3 LED4 Shut down Standby 75%≤SOC≤100% flash ©Dyness reserves the copyright of this document.
  • Page 11: Battery Management System(Bms

    When battery's temperature is beyond range of -20 C~+55 C during discharging, temperature protection starts, device stops supplying power to the outside. The protection is over when it recovers to rated return range. ©Dyness reserves the copyright of this document.
  • Page 12 RV12200 Unit User Manual Other Protection Short Circuit Protection: The battery does not allow external short circuit, which will damage the BMS. CAUTION Battery's maximum discharging current should be more than load's maximum working current. ©Dyness reserves the copyright of this document.
  • Page 13: Installation And Configuration

    The storage time must be less than 3 months in 35~40  Relative humidity: 5%~85% RH  Elevation: no more than 4000m  Operating environment: Indoor installation, sites avoid the sun and no wind, no  conductive dust and corrosive gas. ©Dyness reserves the copyright of this document.
  • Page 14 No flammable, explosive and other dangerous articles are placed beside the  battery.Firefighting equipment should be provided near the equipment, such as portable dry powder fire extinguisher.If necessary, an automatic fire fighting system should be equipped. ©Dyness reserves the copyright of this document.
  • Page 15 Bolt cross three combination bolt User Manual User manual Parallel cable- positive /25mm2/L250mm Parallel cable- Black negative /25mm2/L250mm Engineering coordination Attention should be paid to the following items before construction:  ©Dyness reserves the copyright of this document.
  • Page 16: Equipment Installation

    Equipment installation Table 3-1 Installation steps Step1 Installation preparation 1. Confirm that the light on the front panel of RV12200 unit is off to ensure no live operation Step2 Mechanical installation 1. Battery placement position determination 2. Confirm the direction of battery module installation 3.
  • Page 17 Current:I =Inverter Power/10V Schematic diagram of the wiring operation of the positive and negative terminals of the module 1. Unscrew the plastic nut on the plastic protective cover on the top of the terminal ©Dyness reserves the copyright of this document.
  • Page 18 3. Remove the nut and washer on the terminal, and connect it with the parallel cable or the total positive and total negative cable, torque 10-12NM. After the cable connection is done, reinstall the plastic protective cover. ©Dyness reserves the copyright of this document.
  • Page 19 RV12200 Unit User Manual Wiring diagram for single module use The battery power cable is connected to the MCB according to the following figure. Wiring diagram for parallel use of modules ©Dyness reserves the copyright of this document.
  • Page 20 RV12200 Unit User Manual WARNING The battery can only be used in parallel.Do not use in series.There is a risk of battery damage when used in series. ©Dyness reserves the copyright of this document.
  • Page 21: Use, Maintenance And Troubleshooting

    EPS(backup ACoutput Min.parallel side)ACoutput System energy(kWh) power amount power ≤1.2kW 2.56 ≤2.4 kW 5.12 ≤3.6 kW 7.68 ≤4.8kW 10.24 ≤6.0kW 12.8 Equipment The battery's long-term continuous charging current Charge requirements should be≤0.5C; ©Dyness reserves the copyright of this document.
  • Page 22: Alarm Description And Processing

    Alarm description and processing When the protection action or fault occurs in the system, the alarm signal will be given through the working status indicator on the front panel of the RV12200. You can query the specific alarm categories through battery monitor.
  • Page 23: Analysis And Treatment Of Common Faults

    Power connection check the cause of of power on, and the short-circuit the short circuit red light is on If you have any technical help or question, please contact the seller in time. ©Dyness reserves the copyright of this document.