6| Commissioning

6.1

Preparations for start-up

The compressor has undergone trials in the factory and all functions have been tested. There are
therefore no special running-in instructions.
Check the compressor for transport damage!
6.2

Pressure integrity test

The compressor has been tested in the factory for pressure integrity. If however the entire system is
to be subjected to a pressure integrity test, this should be carried out in accordance with UL 207 or a
corresponding safety standard without the inclusion of the compressor.
6.3

Leak test

Carry out the leak test on the refrigerating plant in accordance with UL 207 or a corresponding
safety standard, while always observing the maximum permissible overpressure for the compressor.
6.4

Evacuation

First evacuate the system and then include the compressor in the evacuation process.
Relieve the compressor pressure.
Open the suction and pressure line shut-off valves.
Evacuate the suction and discharge pressure sides using the vacuum pump.
At the end of the evacuation process, the vacuum should be < 1.5 mbara (0.02 psia) when the pump
is switched off.
Repeat this process as often as is required.
© Danfoss | Climate Solutions | 2024.04
To protect the compressor against inadmissible operating conditions,
high pressure and low pressure pressostats are mandatory on the
installation side.
Risk of bursting!
The compressor must only be pressurized using nitrogen (N
Never pressurize with oxygen or other gases!
The maximum permissible overpressure of the compressor must
not be exceeded at any time during the testing process (see name
plate data)! Do not mix any refrigerant with the nitrogen as this
could cause the ignition limit to shift into the critical range.
Do not start the compressor if it is under vacuum. Do not apply
any voltage - even for test purposes (must only be operated with
refrigerant).
Under vacuum, the spark-over and creepage current distances of the
terminal board connection bolts shorten; this can result in winding and
terminal board damage.
AQ450438640296en-US0301 | 25
US
).
2

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the BOCK UL-HGX66e and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

This manual is also suitable for:

Bock ul-hgx66e/1340 ml 31Bock ul-hgx66e/1340 s 37Bock ul-hgx66e/1540 ml 36Bock ul-hgx66e/1540 s 42Bock ul-hgx66e/1750 ml 44Bock ul-hgx66e/1750 s 50 ... Show all

Table of Contents