Download Print this page

Huawei LUNA2000-2.0MWH Series Quick Manual page 17

Smart string ess
Hide thumbs Also See for LUNA2000-2.0MWH Series:

Advertisement

No.
Cable Hole
1
DC power cable hole
2
AC input power cable or ground cable hole
3
Optical cable or FE communications cable hole
4
UPS or RS485 cable hole (reserved)
(Optional) Connecting Socket Cables
5.2
This procedure applies only to the models listed in the table below.
Model
LUNA2000-2.0MWH-1HX
LUNA2000-2.0MWH-2HX
LUNA2000-2.0MWH-HE2HX
Cables 1733, 1735, 1734, and 1736 are pre-installed.
Cables 1751, 1752, 1757, 1760, 2055, 2056, 1761,
and 1762 need to be installed.
The cables to be installed can be obtained from the
cable binding position shown in the figure.
Air Conditioner Position in the Battery Cabin
1/3/5/7/9/11
1/4/7/10
No.
Meaning
Cable binding
1
position
16
Before installing
cables, remove the
cover from the control
unit cabin.
After cables are
installed, reinstall the
cover to the control
unit cabin and seal the
cable holes at the
bottom with sealing
mud.

Advertisement

loading