Heavy oil preparation ring
!
WARNING: make sure that the feeding line is properly dimensioned and is in compliance the local safety rules and code of practise in the
country of installation.
All installations using heavy oil burners have
to be completed with a forced oil preparation
ring in order to guarantee oil supply to the
burner at suitable temperature and pressure
(temperature +/- 50° C, pressure 3 bar).
For heavy oil with more than 50°E at 50°C
Ecoflam recommends to lower the maximum
output of 10-20% and work in excess of air in
order to grant better operation and reduce
maintenance.
Installation with heavy oil must provide to
the burners:
- CONSTANT PRESSURE
- CONSTANT TEMPERATURE
To size correctly the ring for the heavy oil supply
consider the diagram of the pre-heating
temperature of the heavy oil according to
viscosity and the pump pressure according to
temperature.
Ecoflam heavy oil and dual fuel heavy oil
burners do have in the electrical panel the fuel
temperature device GEFRAN that adjusts the
temperature of the heavy oil and grants
temperature stability.
RACOMMENDED OIL SUPPLY PRESSURE
420010466301
STANDARD SYSTEM COMPOSITION FOR LIGHT OIL
AND HEAVY OIL HEATING AND PUMPING UNIT
I. Feeding and filtering system
II. Fuel heating system for reducing oil viscosity
plus service tank
III. Forced oil supply system "RING"
OIL PREPARATION UNIT
Ecoflam heavy oil burners are delivered
with electrical pre-heater assembled into
the burner body or in a separate skid.
Additional Forced system "OIL RING"
can be design and delivered assembled
on skid/frame or offered as single
component.
ACCESSORIES
Service tanks + Pumps units.
Quotation on request depending on
output and configuration.
bar 6
5
4
3
2
1
0
5
0
Oil temperature
1
0
0
1
5
0
11
EN

Advertisement

Table of Contents
loading

Table of Contents