• Consult the inverter's manual to accurately match settings with your
specific battery and cable arrangement. Adjust settings for optimized
performance and system safety.
• Check 'Activate Battery' when ready to bring the battery online after
completing settings.
4. Check BMS Lithium Batt: Ensure this value is set to 00.
5. Check Use Batt V: This serves as the default for battery
communications should BMS communications fail.
6. Activate Battery: After confirming the above settings, activate the
battery to bring it online and proceed to the charge tab settings.
Charge Tab Settings:
1. Set the 'StartV' for the voltage at which charging should initiate.
Example: "49.0V".
2. Set the 'Start%' for the state of charge percentage at which charging
should start. Example: "30%".
3. Float V = 55.7 V
4. Absorption V = 56.0 V
5. Equalization V = 56.0 V
Discharge Settings:
1. Shutdown 46.0 V / 10%
2. Low Batt 47.5 V/ 10%
3. Restart 52.0 V/ 11%
Smart Load Management:
• For AC-coupled micro inverters into the Gen port, refer to the AC
Coupling Guide.
Saving Settings:
• After configuring all parameters, click 'OK' to save settings.
• To exit without saving, click 'CANCEL'.
©2024 Power Center
Duracell is a registered trademark of Duracell U.S. Operations, Inc., used under license. All rights reserved.
Manufactured under license and warranty supported by Omega Green Power in San Jose, CA.
Max Hybrid 15 kW
Max Hybrid 15 kW
Setup Guide | Commissioning
7