Startup/Shutdown Procedure; Check Before Startup/Shutdown Procedure; Startup Procedure - PrimeVOLT PV 2KTL-S1/G2P User Manual

Single phase grid-tied pv string inverter
Hide thumbs Also See for PV 2KTL-S1/G2P:
Table of Contents

Advertisement

6 Startup/Shutdown Procedure

6 Startup/Shutdown Procedure
6
Startup/Shutdown Procedure
6.1

Check before startup/shutdown Procedure

Check following this steps after installation.
No.
Items
1
The inverter is firmly installed.
2
There is enough heat dissipation space, no external objects or parts left on the inverter.
3
It is convenient for operation and maintenance.
4
The wiring of the system is correct and firm.
5
Check whether the DC and AC connections are correct with a multimeter, and whether there is a
short circuit, break, or wrong connection.
6
Check whether
7
The vacant ports have been sealed; all gaps at the cable inlet and outlet holes have been plugged
with fireproof/waterproof materials, such as fireproof mud.
8
All safety labels and warning labels on the inverter are complete and without occlusion or alteration.
6.2

Startup Procedure

Startup procedure following the procedures :
Supply Main Switch
See if there's any on site
(The figure is only for reference)
AC Circuit Breaker
Switch to ON
(The figure is only for reference)
PV Switch
Switch to ON
LED icon
Blue on (normal status)
Finishing
the waterproof nuts of each part are tightened.
1
2
3
4
5
Your system has started up
ON
OFF
OFF
ON
35