Vent Clearances And Framing; Pipe Clearances To Combustibles; Wall Penetration Framing/Firestops - Heat & Glo TRUE-36G-IFT Installation Manual

Hide thumbs Also See for TRUE-36G-IFT:
Table of Contents

Advertisement

5 5

Vent Clearances and Framing

A. Pipe Clearances to Combustibles
WARNING! Risk of Fire! Maintain air space clearance
to vent. DO NOT pack insulation or other combustibles:
• Between ceiling 昀椀restops
• Between wall shield 昀椀restops
• Around vent system
Failure to keep insulation or other material away from
vent pipe could cause overheating and 昀椀re.
Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).
• DVP heat shield - designed to be used on a wall 4 in. to 7-1/4 in. (102 mm to 184
mm) thick.
• If wall thickness is less than 4 in. the existing heat shields must be field trimmed. If
wall thickness is greater than 7-1/4 in. a DVP-HSM-B will be required.
• If wall thickness is less than 4-3/8 the existing heat shields must be field trimmed.
If wall thickness is greater than 7-5/8 in. a DVP-HSM-B will be required.
(DVP Pipe Shown)
Heat
Shield
3 in. (76 mm)
top clearance
1 in. (25 mm)
clearance around
vertical sections
Figure 5.1 Horizontal Venting Clearances To Combustible
Materials
B. Wall Penetration Framing/Firestops
Combustible Wall Penetration
Whenever a combustible wall is penetrated, you must
frame a hole for the wall shield 昀椀restop(s). The wall shield
昀椀restop maintains minimum clearances and prevents cold
air in昀椀ltration.
• The opening must be framed on all four sides using the
same size framing materials as those used in the wall
construction.
• DVP pipe - A wall shield 昀椀restop is required on one side
only on interior walls. If your local inspector requires a
wall shield 昀椀restop on both sides, then both wall shield
昀椀restops must have a heat shield (refer to Section
12.A.) attached to them.
• See Section 7.E. for information for regarding the instal-
lation of a horizontal termination cap.
Heat & Glo • TRUE-36-IFT, TRUE-42-IFT, TRUE-50-IFT Installation Manual • 2461-980 Rev. Y • 6/23
3 in. (76 mm)
top clearance *
Heat
Shield
1 in. (25 mm)
clearance
Wall
bottom & sides
Shield
Firestop
WALL
Non-Combustible Wall Penetration
If the hole being penetrated is surrounded by non-com-
bustible materials such as concrete, a hole with diameter
one inch greater than the pipe is acceptable.
Whenever a non-combustible wall is penetrated, the wall
shield 昀椀restop is only required on one side and no heat
shield is necessary.
DO NOT PACK WITH
INSULATION OR OTHER
MATERIAL
10 in.
12 in.
A*
MODEL
TRUE-36
NG/Propane
TRUE-42 NG
TRUE-42
Propane
TRUE-50
NG/Propane
* Shows center of vent framing hole with minimum vertical for top venting. The
center of the hole is one (1) in. (25 mm) above the center of the horizontal
vent pipe.
Figure 5.2 Wall Penetration
B
A*
B
74-3/16 in.
73-3/16 in.
79-3/16 in.
78-3/16 in.
91-3/16 in.
90-3/16 in.
83-3/16 in.
82-3/16 in.
31