Changing The Syrup Pan; Evaporator Shutdown; Table 5 | Potentiometer Guide For Combustion Chamber Fuel Reloads - Lapierre FUSION X2 User Manual

Evaporator
Table of Contents

Advertisement

SECTION 5 Start-up, operation and shutdown procedures (continued)

TABLE 5 | Potentiometer guide for combustion chamber fuel reloads

POTENTIOMETER GUIDE FOR COMBUSTION CHAMBER FUEL RELOADS
BEFORE the reload
Immediately AFTER the reload
AFTER 2 minutes
5.2.3

Changing the syrup pan

Below are the instructions to follow when changing the syrup front pan.
• Check the condition of the gasket between the pans and the combustion chamber.
• Check the insulation joints between the pans.
- IMPORTANT:
o a syrup soiled gasket must be cleaned,
o a blackened or damaged gasket must be replaced immediately or very quickly.
• Check that there are no concentrate leaks under the boiling rear pan.
• Check the boiling rear pan for cleanliness and accumulation of sugar stones.
• Before replacing the syrup front pan, make sure the fireproof bead is fully raised to its position.

5.3 EVAPORATOR SHUTDOWN

Below are the instructions for shutting down your evaporator.
• Make sure you have a minimum reserve of 2 hours of concentrate or water.
• Stop feeding the combustion chamber.
• Although the coals burn out quickly it should be noted that the heating of the pans will continue for some
time due to the accumulated heat in the evaporator.
• Turn the key to the Off position. Note that all fans will continue to run for a period of 2 hours.
• After 2 hours:
- turn Off the water or concentrate supply to the evaporator,
- close the valve located between the boiling rear pan and the syrup front pan,
- if applicable, close the valves between the syrup pans.
Lapierre Equipment |
FUSION X
2
EVAPORATOR
PRIMARY = Ø (Zero)
PRIMARY = 2
PRIMARY = 4
| USER MANUAL | Version 01 - September 2022
21
SECONDARY = Ø (Zero)
SECONDARY = 4
SECONDARY = 2

Advertisement

Table of Contents
loading

This manual is also suitable for:

F5F5 turbo

Table of Contents