Delayed Activation of Slaves
Example 2: JMP/JME
Programming (C1000H and
C2000H PCs)
42
Artisan Technology Group - Quality Instrumentation ... Guaranteed | (888) 88-SOURCE | www.artisantg.com
The section of the following program between JMP and JME will not be exe-
cuted until the I/O verification error is cleared (i.e., until all Slaves are turned
on). The initial and main programs will thus be executed only after all Slaves
have been turned on.
12800
25310
(I/O verification error)
12801
25313
(Normally ON)
12801
25502
1 sec clock
25310
(I/O verification error)
12803
12802
12803
12802
Section 3-4
12801
JMP(04) 01
12800
Initialization program
Main program
JME(05) 01
DIFU(13) 12802
12803
FAL(06) 00
END(01)