First Inspection After Installation Or Repair - Siemens SIMOTICS XP Eagle Line 1MB1.33 Operating Instructions Manual

Low-voltage motors, shaft heights 71...315
Table of Contents

Advertisement

9.2.3

First inspection after installation or repair

Perform the following checks after approximately 500 operating hours or at the latest six
months after commissioning:
Table 9- 1
Checking
The electrical parameters are maintained.
The permissible bearing and winding temperatures are not exceeded.
The smooth running characteristics and machine running noise have not
deteriorated.
The foundation has no cracks or indentations. (*)
(*) You can perform these checks while the motor is running or at a standstill.
Additional tests may also be required according to the system-specific conditions.
NOTICE
Machine damage
When carrying out the inspection, if you detect any impermissible deviations from the
normal state, you must rectify them immediately. They may otherwise cause damage to the
machine.
1MB1.33 Eagle Line shaft heights 71 ... 315
Operating Instructions, 08/2023, A5E52990459A
Checks after assembly or repair
Maintenance
9.2 Inspection and maintenance