IN ORDER FOR THE CONVEYOR TO BE STABLE, THE SUPPORTS
WARNING
!
MUST BE LAGGED TO THE FLOOR OR SUPPORT STRUCTURE.
THIS IS THE CUSTOMER RESPONSIBILITY!!
Titan Zero Pressure Accumulators have been assembled and test run
at the factory so very little adjustment is necessary after the units have
been field assembled. The following information will help with initial
installation of possible part replacement.

FRAME ASSEMBLY

1. Along side the area where the conveyor is to be installed, layout the frame sections in their proper position
according to the ordered description or refer to your copy of the approval drawing. If the frame placement
has not been shown Titan recommends that the drive section be placed approximately in the center of the
overall conveyor length. This is especially important for conveyors over 30 foot in length.
NOTE: IF SEvERAL SEcTIONS OF FRAME ARE TO bE jOINED IN A pARTIcULAR
SEqUENcE, ThEY wILL bE FAcTORY MATchED MARkED. SEE FIGURE 2.
2. Layout a line on the floor to represent the centerline of the conveyor. As frame sections are bolted
together make sure they remain centered on the line.
3. Bolt together conveyor frames finger tight. Square frames and make sure all frames line up with adjacent
sections before securing all bolts. The frames must be level for proper operation. Adjust the supports as
necessary for leveling.
4. Take off conveyor chain guards and with strands of chain provided, connect the end rollers from one frame
section to another. See FIGURE 3.