Tower-Mounted Installation; Installing The Ups And Lead-Acid Batteries - Huawei UPS2000-H Quick Manual

Hide thumbs Also See for UPS2000-H:
Table of Contents

Advertisement

UPS2000-H-(6 kVA-10 kVA)
Quick Guide
Figure 1-7 Installing the UPS and batteries
----End

1.2.2 Tower-Mounted Installation

1.2.2.1 Installing the UPS and Lead-Acid Batteries

Procedure
Step 1 Assemble the support bases.
Figure 1-8 Assembling a support base
Step 2 Place the UPS and batteries on the support bases.
Issue 03 (2023-08-20)
Copyright © Huawei Digital Power Technologies Co., Ltd.
1 Installation and Cable Connection