Install Cisco NCS 1001
Figure 15: Four Post Left/Right Side Slide Rails
1
2
3
The front and rear vertical rails of four post racks must be within this range (547 to 847 mm) to install NCS
1001. NCS 1001 cannot be installed on a four post rack if the distance between rails is outside this limit.

Install NCS 1001-K9 into EIA/ANSI Rack

In an EIA/ANSI rack, NCS 1001 can be installed in the front position.
Note
Caution
It is required to have 100 mm (3.94") space on the front and rear side of the rack to provide sufficient clearance
for cable routing and cooling of the system.
In case of a closed cabinet, the cabinet must support the thermal management or front/rear doors need to have
70% perforation. Closed cabinets must have adequate airflow to dissipate maximum power from equipments
in a fully-equipped cabinet.
NCS 1001-K9 shall be installed maintaining a minimum clearance of 5mm above and below the chassis.
Before you begin
Ensure the rack is compatible. See the Rack Comatibility section.
Mounting depth - Minimum is 547 mm and Maximum is 847 mm
Front rail mating surface
Rear rail mating surface
The rack is not provided by Cisco. Cisco provides only the chassis and the sliding rail.
Use only the fastening hardware provided with NCS 1001-K9 to prevent loosening, deterioration, and
electromechanical corrosion of the hardware and joined material.
Install NCS 1001-K9 into EIA/ANSI Rack
Hardware Installation Guide for Cisco NCS 1001
19

Advertisement

Table of Contents
loading

Table of Contents