Section 10
Testing IED operation
If some setting deviates, check the analog input settings under
Main menu /Configuration /Analog modules
IEC10000032 V1 EN-US
Figure 20:
10.7

Testing the protection functionality

Each protection function must be tested individually by secondary injection.
Verify operating levels (trip) and timers.
Verify alarm and blocking signals.
Use the disturbance handling tool in PCM600 to evaluate that the protection function has received
the correct data and responded correctly (signaling and timing).
Use the event viewer tool in PCM600 to check that only expected events have occurred.
80
If the IEC/UCA 61850-9-2LE communication is interrupted during current injection, the
disturbance report tool in PCM600 will display the current that was injected before the
interruption.
PCM600 disturbance report tool display after communication interruption
© 2017 - 2023 Hitachi Energy. All rights reserved
1MRK506371-UUS Rev. M
IEC10000032-1-en.vsd
GUID-125B6F28-D3E5-4535-9CD6-6C056B79F496 v2
Line distance protection REL670
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion rel670

Table of Contents