Shut Down

Normal Unit Shutdown

Figure 18. Normal unit shutdown

Extended Shutdown Procedure

If the system is taken out of operation for long periods of time,
use this procedure to prepare the system for shutdown.
1. Test condenser and high side piping for refrigerant leakage.
2. Open electrical disconnect switches for evaporator water
pump. Lock the disconnect in an open position.
3. Open the unit main electrical disconnect and unit- mounted
disconnect and lock in open position.