Shut Down; Normal Unit Shutdown; Extended Shutdown Procedure - Trane Cold Generator CICD Series Installation, Operation And Maintenance Manual

Compact chiller 30 to 75 tons (60 hz), r-410a
Table of Contents

Advertisement

Shut Down

Normal Unit Shutdown

Figure 18. Normal unit shutdown

Extended Shutdown Procedure

If the system is taken out of operation for long periods of
time, use this procedure to prepare the system for
shutdown.
1. Test condenser and high side piping for refrigerant
leakage.
2. Open electrical disconnect switches for evaporator
water pump. Lock the disconnect in an open position.
3. Open the unit main electrical disconnect and unit-
mounted disconnect and lock in open position.
CG-SVX044B-EN
37