Installing the transducer

Installing the transducer cables

When the transducer has been placed under its mounting location, the cables can be pulled
through the steel conduit up to the Transceiver Unit.
Prerequisites
In order to do this task, the following prerequisites must be met.
• All relevant work instructions, procedures and standards must be available.
• The mounting ring has been installed.
• The steel conduit is mounted with all installation work finalized.
• All relevant drawings have been approved by the classification society.
• All relevant personnel (skilled shipyard workers, ship electricians) and their tools must
be available.
You must be equipped with a standard set of tools. This tool set must comprise the normal
tools for electronic and electromechanical tasks, such as screwdrivers, pliers, spanners, a
cable stripper etc. Each tool must be provided in various sizes. We recommend that all tools
are demagnetized to protect your equipment.
The following tools and consumables are required.
• Fish tape (wire pulling tool) with suitable length
• Electrician's tape
Context
All necessary precautions must be made to avoid damage to the cables while pulling them
through the steel conduit.
Note
Make sure that all welding has been finalized before you pull the cables through the steel
conduit. Heat may cause serious damage to the cables and the transducer.