Chapter 2
Installation Procedure
Install Mounting Hardware
1. Remove the front
covers with locking
doors to reveal the
panel interior.
2. Align the panel to the
desired mounting
location and mark all
keyhole locations.
Install ERP24-FT up to
•
two high.
Install any number of
•
ERP24-FT or ERP48-FT
panels side-by-side, in
direct contact, with the
removable plates on the
shared sides removed as
needed.
Allow clearances as
described on
3. Set the panel aside.
4. Pre-drill then install the
required mounting
hardware for mounting
the panel using the
previously marked
reference points as a
guide.
ERP24-FT requires four
•
6–8 mm (1/4–3/8 in)
bolts or screws, 50–
100 mm (2–4 in) long and suitable wall plugs
Both the surface and mounting hardware must support 23 kg (50 lbs).
-
Expose at least 25 mm (1 in) of threads for mounting the panel.
-
ERP48-FT requires six 6–8 mm (1/4–3/8 in) bolts or screws, 50–100 mm (2–4 in) long and
•
suitable wall plugs.
Both the surface and mounting hardware must support 46 kg (100 lbs).
-
Expose at least 25 mm (1 in) of threads for mounting the panel.
-
Mount the Panel
1. Mount the panel to the installed mounting bolts.
2. Tighten the bolts securely.
3. Check for a plumb installation and follow all local code restrictions.
14
page 9
.
394 mm
(15.5 in)
394 mm
(15.5 in)
441 mm
(17.35 in)
394 mm
(15.5 in)
ERP24-FT24
394 mm
(15.5 in)
Relay Panel Feedthrough Installation Manual
441 mm
(17.35 in)
394 mm
(15.5 in)
394 mm
(15.5 in)
ERP48-FT48
495 mm
(19.5 in)
120.1 cm
(47.3 in)