● Do not bind signal cables and power cables together.
● RS485 cables and FE cables must be shielded cables.
● The cable connection between the UPS and the SmartLi is used as an example
Figure 4-146 Installing a signal cable between the UPS and the SmartLi
(1) Monitoring interface unit in the master SmartLi cabinet
----End

4.10 Installing a Top Enclosure Frame

If cables are routed in and out from the bottom, install a top enclosure frame.
4.10.1 Bottom Cable Routing (400K–600K, Three-Phase Four-
Wire)
Step 1 Remove the connecting kits from both sides of the cabinet top.
Issue 07 (2023-03-20)
NO TICE
in the figure.