5 Switching on the system

Perform the following checks and works while mains supply is switched off before
switching on the ONLITE central CPS system:
Check all works done and compare the established connections with the given plans and
drawings.
Make sure that all connections are firm.
d
Danger
When checking the battery connectors there is a risk of mortal danger.
Use only insulated tools. Wear rubber gloves, protective goggles and protective
clothes (incl. safety shoes) and take off metallic objects e.g. watches and jewellery.
Remove all unused cables, insulation and fixing materials, tools and packaging.
To switch on the ONLITE central CPS system, proceed as follows:
1. Switch on the external main switch.
2. Check the voltage supply at the terminals L1, L2, L3 and N of the terminal block -2X1.
3. Check the rotational direction of the voltage supply.
4. Check whether all outgoing fuses of the circuits (F1 - F20 blue, F1 - F20 red) in the sub
distributions are opened.
5. Reinstall the fuses 2F1, 2F2, 2F10.1 and 2F10.2.
d
Danger
The System is now connected and energised. Mortal danger by electrical shock.
6. Close the first fuse in the first sub distribution (outgoing fuse F1).
a All luminaires installed in this circuit are switched on (status "ON").
7. Check whether the number of switched on luminaires and their installation location comply
with the given plan.
8. If the number of luminaires and their installation location is correct, switch off the circuit by
opening the fuse.
9. Repeat the luminaires check for all sub distributions and circuits.