Checking After Installation
Check the drainpipes are securely installed, clear, free of leakage and n
ot over bent;
Wrap the chilled water connector with heat insulation cotton tightly;
Check that the floats are leveled and the impurities, such as cables and
insulation foam, are cleaned. Cables are securely bound and not on the wa
ter pan;
Verify that the distance between two chilled water pipes outside the cabi
net is sufficient (recommended distance: longer than 25 mm), the hose is
tightly wrapped with insulation foam, and that junctions are secured usin
g glue;
Check that the pipe lines have completed pressure preservation and air ti
ghtness test;
Check that the cabinet is grounded;
Check that power cables and signal cables are correctly connected, protec
ted in a corrugated pipe, and bound securely. Check that power cables are
routed separately from signal cables to avoid interference from strong cu
rrents on signal cables.