10 Commissioning
Corrosive chemicals!
▶ Risk of caustic burns.
Wear suitable protective gear.
●
Completely drain the plant.
●
Leakage
▶ Emission of dangerous materials.
Provide precautionary measures against exceeding the
●
maximum permitted pressures caused by pressure
surges (water hammer).
Cleaning agent
▶ Damage to the GEMÜ product.
The plant operator is responsible for selecting the clean-
●
ing material and performing the procedure.
1. Check the tightness and the function of the product (close
and reopen the product).
2. Flush the piping system of new plant and following repair
work (the product must be fully open).
ð Harmful foreign matter has been removed.
ð The product is ready for use.
3. Commission the product.
4. Commissioning of operators in accordance with the en-
closed instructions.