3. Installation

Unpacking and Safety Precautions

Before unpacking the DC power system, note any physical package damage that could indicate
potential damage to the contents. After removing the components from their boxes and packing
material, inspect for any shipping or other damage. Always consider personal safety. Remove all metal
jewelry before beginning the installation. Care should be taken during the installation process to
prevent exposure of the equipment to wire clippings. If possible, rectifiers should remain in their
shipping boxes until the shelf wiring is complete.

Installation Tools

Wire cutters and strippers
Digital meter, +/- 0.02%
Heat shrink gun
Screw Drivers (#1 and #2 Phillips)
Torque wrench (0-240 in-lb / 28 Nm)
Cable crimpers
5/16", 7/16", ½" and 3/8" nut drivers and sockets

Torque Settings

The following table lists the recommended torque settings for all mechanical and electrical
connections according to screw and nut size.

Frame Mounting

The CPS6000 system is designed for a standard 19-inch or 23-inch wide equipment racks. The system
should be installed with a minimum gap of 3/4 inch below the system to allow proper airflow. Attach
the system to the frame using a minimum of 12 (six on each side)
12-24 screws included with the shelf. Weights of the systems is shown in the following table.
Page 13
© 2021 ABB. All rights reserved.
Screw or Nut Size
4-40
6-32
8-32
10-32
12-24
¼-20
5/16-18
3/8-16
Table 2: Torque Settings
CP:S6000_External Distribution_IG
Torque
Nm
1.5
4.25
5.75
7.5
15.3
27.1
In-lbs.
12
22
37
50
65
135
240
Rev. 1.3